Construction - Man hours calculation - Pipe welding time calculator




Man-hours calculation — Piping welding: Welding efficiency.


Piping Works — Man Hour Calculation for Pipe Welding

Calculation of the number of inches diameter of welding.
First of all, we will divide the welding of pipes into two large groups:
1 - Piping where the final quality control is performed by hydrostatic testing.
2 - Piping where, in addition to the hydrostatic test, the quality control is carried out with non-destructive tests (e.g. RT or UT).

ENGINEER - CONSTRUCTION - ESTIMATING PIPE WELDING MAN HOURS - PIPE WELDING TIME CALCULATOR

At present, for piping works, the contractors do the engineering, for example: by isometric drawing, pipe model that allows a fast construction in the workshop and an easy assembly on site.



We divide each isometric line into sections called spools for fabrication in the shop.
Once the spools are manufactured, we transport them to the construction site for their adjustment, positioning and the execution of the adjustment welds.
In general, with good engineering, the number of welds performed in the prefabrication phase is between 70 and 90% of the total to be performed.
This not only reduces costs and man-hours.
It also improves the possibilities of meeting the construction deadlines by reducing the incidence of weather conditions in the process of work execution.

It has been proven that welds made in the workshop are faster and with better quality control than those made in the field.

We must also understand that welding times vary depending on the material we are working with. 
For the moment we will refer to carbon steel pipes.

It is also necessary to understand that the welding time varies according to the thickness of the pipe (the thicker the pipe, the more time we have to prepare the bevel and the more welding work we have to do because we have to fill more).

It should also be noted that the larger the diameter of the pipe, the more difficult it is to handle.

Finally, we give here the standard times (we emphasize that speaking of standard times means that the operators have no economic incentive to make an effort to achieve a higher performance).
For the first type of welding (where the quality is controlled only by the hydrostatic test) and for a standard 4-inch carbon steel pipe, the crew time for one inch of welding is
0.70 MAN HOURS * inch, for field welding, and 0.40 MAN HOURS * inch, for prefabricated welding. 
The crew consists of a helper, a journeyman and a welder).
If the crew works 10 hours per day, each group will produce approximately 42 field and 75 shop inches per day.


Look out!
 
This applies to work done under standard conditions. For more information, see my book "Estimator's Piping Man-hours Tool"

For the second type of welding (here the quality is controlled with non-destructive test, besides the hydrostatic test) and for the same diameters, the times for inch of welding in the field, will be of 2 MAN HOURS * inch, welding and 1 MAN HOURS * inch, welding in prefabricated.
The production for 10 hours of work is for each group of 15 and 30 inches per day.
Read more in Calculate man hours


Look out!
 
This applies to work performed under standard conditions. For further information, please refer to my book "Estimator's Piping Man-hours Tool"

Note:
The time includes:
Piping welding
It does not include:
Complicated handling of piping.
Painting.
Insulation.
Supports.
Clamps.
Scaffolding for piping.

Feb 16, 2019

Construction estimator skills

Skills for Construction Estimators

Basic skill

The estimator needs basic innate skills for successful professional development. Of course, these skills are developed with experience, but the estimator must have at least certain innate skills to perform the job.
Anyone who wants to enter the estimating profession should have a combination of the core skills listed in Figure 1.


The picture depicts the basic skills required for an estimator.

Math skills

Estimation by its very nature requires the formulation of numerous mathematical operations and complex calculations.
Mathematical literacy is essential for beginners.

Communication skills

Another necessary skill is the beginner's natural ability to develop good oral and written communication.
The success of the project is often hidden in the details and their correct evaluation.
In most situations, it is necessary to communicate on a routine basis with
Colleagues who specialize in the type of project in question.
Equipment and service providers.
The client.
With subcontractors.
Or with attendees at business meetings.
Good writing is another critical skill that will help you present complex reports clearly and concisely.

Perseverance or persistence 

This trait is a hidden gem, but essential to the estimator's personality. 
Estimators must be persistent. 
Perseverance is used, for example, in the painstaking effort to find the best price for an infinite number of materials for a project in a universe of suppliers. 
Perseverance enables the estimator to complete all aspects of the bid in a timely manner, regardless of the effort required.

Honesty and reliability 

Evaluation work requires honesty and reliability. 
These qualities are required by:
The company's shareholders, who are interested in the economic success and prestige of their company. 
Your own colleagues, who will manage projects based on the appraiser's preliminary analysis.

Jan 19, 2019

How to choose a Contractor

How do I choose a contractor?

Selecting a Contractor Checklist

Image of the cover of a podcast about, How to choose a Contractor
In this audio, number 3, we discuss the key functions of the client's purchasing department and the role it plays in selecting the most appropriate contractor. 

Jan 12, 2019

How to Estimate

How to Estimate

How do I perform construction and industrial assembly?

Podcast #2.



Image of the cover of a podcast about how to estimate

How to do an estimate? In this audio, which is the second in a series of podcasts, the tasks that an estimator or a group of estimators typically perform to quote a project and the skills that are most in demand in the research profile of a successful estimator are disseminated..

Jan 6, 2019

How to perform construction and industrial assembly.

How to do construction work?

How to perform industrial construction and assembly work



Image of the cover of a podcast about: How to execute Construction Works and Industrial Assemblies.
Podcast#1

General information

In this first podcast, we share generalities about how to estimate industrial construction and assembly work.